Major Ongoing Projects

English
Image: 

In order to strengthen core processes and modernize, HPCL has developed ambitious plans for expansion and diversification in the areas of increasing energy demand, technological upgradation and environment management. HPCL has proposed capital expenditure (including equity investments in Joint Ventures) of Rs. 11487 Crores during the eleventh plan. A brief on some major projects in progress in different parts of India are given below:

Rewari Kanpur Product Pipe Line (RKPL)

Objective of the project is to meet transportation of POL demand through Pipeline which is environment friendly and saving in logistic supply. Total cost of the Project is Rs. 1210.64 Cr. and the project is expected to be completed by November 2015.

The Environmental Clearance (770 KB) PDF File Opens in a new window from The Ministry of Environment and Forests (MOEF) has been obtained.

Click here for Compliance and monitoring reports.

Uran-Chakan / Shikrapur LPG Pipeline Project

Objective of the project is to reduce the Bulk LPG Tanker Movement along with roads between Mumbai and Pune. To improve Safety / Environment along with the Ghat Section between Mumbai and Pune. Total cost of the Project is Rs. 309.83 Cr. A project is being shared on 50:50 basis with M/s BPCL and the project is expected to be completed by October 2014.

Mangalore –Hassan-Mysore LPG Pipeline

Objective of the project is to reduce the Bulk LPG Tanker Movement along with roads between Mangalore-Bangalore & Mysore. To improve Safety / Environment friendly mode of transportation and aslo substantial saving in logistics of supply would be generated. Total cost of the Project is Rs. 701 Cr. And the project is expected to be completed by November 2015.

Awa-Salawas Pipeline Project

Objective of the project is to meet transportation of POL demand through Pipeline which is environment friendly and saving in logistic supply. Total cost of the Project is Rs. 134.43 Cr. and the project is expected to be completed by November 2015.

Diesel Hydro Treating (DHT) at Mumbai & Visakhapatnam Refineries

HPCL is setting up Diesel Hydrotreater Units of 2.2 MMTPA each with associated facilities at Mumbai Refinery (MR) and Visakhapatnam Refinery (VR) to meet Euro-IV specifications for diesel as per the latest Auto Fuel Policy.

The Environmental Clearance for the DHT projects for Mumbai Refinery (346 KB) PDF File Opens in a new window & Visakh Refinery (357 KB) PDF File Opens in a new window have been obtained.

The Environmental Statement (127 KB) PDF File Opens in a new window of Visakh Refinery for the FY 2012-13 has been submitted to Andhra Pradesh Pollution Control Board (APPCB). View the Compliance Status of Environmental Clearance (494 KB) PDF File Opens in a new window Stipulations for DHT VR Project.

The Revised cost of the project is estimated at INR 2174 Crores for Mumbai Refinery and INR 2730 Crores for Visakhapatnam Refinery. The projects are expected to be completed by September 2013.